Successfully completed construction of a gasoline dispatch installation, based on the Techcraft project. A completely new pumping station was designed, in which two pump units with a capacity of 500 m3/h each were installed and connected. In order to ensure appropriate suction conditions, the pumping station was lowered relative to ground level. The valve system allows for supplying pumps from one of the two storage tanks and recirculating liquid back to the tank. The correct and safe operation of the system is monitored by a control and measurement system, the MMS system and gas and fire detection. Due to the location of the pumping station, mechanical ventilation was installed to force air circulation.

The project also included the construction of an approximately 2 km long dispatch pipeline connecting the designed pumping station with the railway loading facility.